Average time frame to implement a planning application
What is the average time frame to implement a planning application using SEM-BPS?
It depends on the complexity of the planning model that is to be developed in SEM-BPS. However, a good estimate would be 5-6 months for an average SEM-BPS project with 8-10 infocubes including transactional ones, 8-10 Planning Areas, 250-300 planning steps and 30-50 users.