Important points for planning a R/3 upgrade project


Amit Jain
Rating: -4.53- (out of 5)

Because the mainstream support for SAP R/3 4.6C ended in Dec 2006 and the extended maintenance will end in December 2007, it's important, or in a way, imperative to upgrade from R/3 4.6. The version we upgrade depends on lot of factors and is entirely driven by the organization's need. This blog highlights some of the critical factors that affect the success of anyupgrade project. This is more from project planning point and has minimal technical content.

1) Technical or functional

The scope of an upgrade project is determined by whether it is a purely technical upgrade or also a functional upgrade. In a technical upgrade, it's mainly the system upgrade and no new functionality is implemented. More or less, the following teams are involved in an upgrade project. The task list is not complete; it's just to give an idea about the nature of work various teams will be involved in.

Sr. no Teams Tasks
1 a)      Unix b) &...

RELATED CONTENT
SAP tips and best practices
Minimizing business disruptions during an SAP upgrade or implementation
Retrieving content from an SAP workflow attachment
Updating URLs in SAP SRM
How to change default settings in SAP SRM
What are the benefits of implementing SAP SRM?
Increase column width in a transaction screen
Updating an RT table entry in SAP HR Payroll -- without the ADDWTE option
Is this the quickest way to find a BADI?
Adding custom fields for retail product comparisons in SAP BW
Improving performance with ABAP Objects in SAP Workflow

SAP implementation and upgrades
Abiomed CIO discusses plans for getting more from SAP applications
Choosing Standard or Enterprise support more difficult for SAP customers with no KPIs
The top SAP advice from the experts in 2009
Six SAP upgrade tips and best practices for global environments
Experts share common global SAP upgrade problems and mistakes – and how to avoid them
Selling used SAP licenses
Ray Wang on SAP's cloud strategy, SaaS options
SAP managed hosting no longer all or nothing
SAP postpones maintenance fee hike
SAP needs to do more with centers of excellence, analyst says

RELATED GLOSSARY TERMS
Terms from Whatis.com − the technology online dictionary
ASAP  (SearchSAP.com)

RELATED RESOURCES
2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
Search Bitpipe.com for the latest white papers and business webcasts
Whatis.com, the online computer dictionary


nbsp;    Basis c)       DBA Disk space, Kernel upgrade, table space, etc.
2 Technical SPDD, SPAU, cloned program and transport sequence
3 a)      Functional b)      Business community   Unit testing and integration testing  

Also check for a SAP GUI version compatible for the upgraded SAP version.

2) System landscape.

The system landscape design will depend on the project plan. To increase the availability of system for production support and new developments, following dual system landscape helps.

Before upgrade

[IMAGE]

After upgrade

[IMAGE]

Retaining the older version system after the upgrade for two to three months helps in resolving post-upgrade issues. The objective should be to minimize dual maintenance window.

3) Dependent SAP systems (BW, SRM,)

The success of the upgrade project depends on the dependent SAP systems like SRM, BW and HR In some cases, you might have to upgrade other SAP systems also -- if the compatibility is an issue, e.g. SRM 3.5 is has compatibility issues with ECC 5.0 .

Some thought should be given to the sequence of the upgrade of these systems. R/3 should be the last one to be upgraded.

4) Dependent non-SAP systems

The non-SAP systems like Manujistic, Taxware and Hyperion etc. also play major role and could spoil the whole upgrade experience. They are critical because due to the differences in vendor, there might be more time lag to find out the exact version or proper support on time.

5) Transport sequence

Transport sequence is very important. If the changes had been done to the objects changed by SPAU or SPDD, those requests should be the transported after the SPAU/SPDD transport requests.

Important care should be taken after upgrade that no request of old version should be moved in upgraded system like request created in 4.6 C be transported in ECC 5.0 (This causes dumps where we move transport which contains objects that have dictionary table changes)

6) Cloned programs

Cloned programs are customer programs copied from standard programs and then made to work for a customer. Cloned program are coded by copying the standard program to a Z-program, having the standard includes or standard function modules.

This causes issues after the upgrade, because the standard includes or functional modules might not work with our custom code.

So make a list, before upgrading, of your entire cloned program and change the same and include them in the test plans.

7) Unicode compliance and obsolete ABAP statements

The amount of ABAP rework depends on whether we are complying with Unicode. The switch to Unicode affects all statements where an explicit or implicit assumption is made about the internal length of a character in custom programs.

Also couple of ABAP statement / tables has become obsolete or more severe check is done during syntax check. E.g.

a)      STOP statement in methods

b)      Table M_VMVLA is replaced with SHP_IDX_GDSI and M_VMVLB is replaced with SHP_IDX_PICK

c)      Usage of Message number 000.

There could be much more example and is customer specific.

8) Test plan

A thorough test plan should be prepared both for functional Users and for Key Business Users, both after development and test environment upgrade. If possible, a tool (e.g. RBE – Reverse Business engineering) should be used that will give you an idea of the important transactions based on the number of times it is used or the transaction run during month end or fiscal year end. These transaction should be a part of testing plan.

9) Post-upgrade activity

After the upgrade, the following points should be planned

a)Job release strategy

b)Security roles 

There could be more points to upgrade planning, but I hope the above points will help in better upgrade planning.

Amit Jain is a SAP technical consultant for Wipro Technologies.


This content is reposted from the SAP Developer Network.
Copyright 2007, SAP Developer Network

SAP Developer Network (SDN) is an active online community where ABAP, Java, .NET, and other cutting-edge technologies converge to form a resource and collaboration channel for SAP developers, consultants, integrators, and business analysts. SDN hosts a technical library, expert blogs, exclusive downloads and code samples, an extensive eLearning catalog, and active, moderated discussion forums. SDN membership is free.

Want to read more from this author? Click here to read Amit Jain's Weblog. Click here to read more about ABAP on SDN.



Rate this Tip
To rate tips, you must be a member of SearchSAP.com.
Register now to start rating these tips. Log in if you are already a member.


Submit a Tip




DISCLAIMER: Our Tips Exchange is a forum for you to share technical advice and expertise with your peers and to learn from other enterprise IT professionals. TechTarget provides the infrastructure to facilitate this sharing of information. However, we cannot guarantee the accuracy or validity of the material submitted. You agree that your use of the Ask The Expert services and your reliance on any questions, answers, information or other materials received through this Web site is at your own risk.



NetWeaver SAP White Papers
About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
SEARCH 
TechTarget provides technology professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective purchase decisions and managing their organizations' technology projects - with its network of technology-specific websites, events and online magazines.

TechTarget Corporate Web Site  |  Media Kits  |  Site Map




All Rights Reserved, Copyright 2000 - 2010, TechTarget | Read our Privacy Policy
SearchSAP.com is a search service provided by TechTarget and is completely
independent of and not affiliated with SAP AG.
  TechTarget - The IT Media ROI Experts