QUESTION POSED ON: 12 January 2003
I have some planned orders in APO that have a finish time on a Saturday morning which is the end of the Friday 18:00 to 06:00 shift. However, R/3 will not recognise this time, and puts the finish date and time to exactly 24 hours before the APO finish date and time. When a change is made on the R/3 side, this date is sent back to APO, causing multiple loading on the scheduling board. I have tried creating the shifts in R/3 to map APO, but this does not seem to work. My clients are reluctant to fix orders in APO, and they want to stick with the resource setting of finish on a non working day.
Any ideas on what I can do to get R3 recognising the Saturday date, or if not, are there any other options in APO?
|