QUESTION POSED ON: 18 November 2003 We are currently on SAP 4.6. Should we go to SAP 4.7 prior to implementing BW or not? Both projects are targeted to happen within a 12-month timeframe. Which one should go first?
>
EXPERT RESPONSE
There are several business functionality factors that determine which one
goes first. You need to understand first what new capability you want to
implement in BW that requires BW upgrade. There were a few presentations on
BW upgrade strategies at the ASUG BITI annual conference on October 26-29,
2003. I would suggest you do a web search and take a look at those presentations. One such presentation Session code: 406 - SAP BW 3.0B upgrade: Best
Practices by Janet Hutchison from Weyth. Good luck.
Search and Browse the Expert Answer Center Search and browse more than 25,000 question and
answer pairs from more than 250 TechTarget industry experts.
TechTarget provides enterprise IT professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective IT purchase decisions and managing their organizations' IT projects - with its network of technology-specific Web sites, events and magazines.
All Rights Reserved, Copyright 2000 - 2008, TechTarget | Read our Privacy Policy SearchSAP.com is a search service provided by TechTarget and is completely independent of and not affiliated with SAP AG.