Implementing SAP BW before R/3

We will have to implement SAP BW along with SAP R/3. Our team is new to SAP implementations and the timeframe is...

very tight. My question is if it's possible to implement BW without having finishing implementing R/3?


Yes, you can implement R/3 and BW in parallel, but I am not a big fan of this approach from the experiences I have faced/heard. I would rather prefer to start BW sometimes during the Business Blueprint phase of the R/3 implementation and would go live after R/3 go-live. On the other hand, if the coordination and knowledge exchange between R/3 and BW teams is very powerful and R/3 implementation does not require mass master data changes and business process reengineering activities, BW and R/3 can be implemented in parallel.


This was last published in February 2003

Dig Deeper on SAP CPM software

PRO+

Content

Find more PRO+ content and other member only offers, here.

Have a question for an expert?

Please add a title for your question

Get answers from a TechTarget expert on whatever's puzzling you.

You will be able to add details on the next page.

Start the conversation

Send me notifications when other members comment.

By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Please create a username to comment.

-ADS BY GOOGLE

SearchManufacturingERP

SearchOracle

SearchDataManagement

SearchAWS

SearchBusinessAnalytics

SearchCRM

SearchContentManagement

SearchFinancialApplications

Close